Burundi - Extension de l'Aéroport de Bujumbura


Project Summary

Approval Date 19 Dec 1980
Signature Date 20 Jan 1981
Planned Completion Date 31 Dec 1985
Last Disbursement Planned Date 31 Dec 1985
Sovereign / Non-Sovereign Sovereign
Sector Transport
DAC Sector Code 21050
Commitment U.A 9,995,755.06
Status Completion

Participating Organization

Funding
African Development Bank
Implementing
Ministère des Travaux Publics et de l'Equipement, Direction Générale des Routes

Information

IATI identifier 46002-P-BI-DA0-001
Last Update 26 Jan 2023

Export

Contact Details

Geographic Location

Country Burundi