Addis Abeba Sewerage Project , phase 1


Project Summary

Approval Date 12 Dec 1975
Signature Date 16 Jan 1976
Planned Completion Date 31 Dec 1979
Last Disbursement Planned Date 31 Dec 1979
Sovereign / Non-Sovereign Sovereign
Sector Water Supply & Sanitation
DAC Sector Code 14022
Commitment U.A 4,604,605.26
Status Completion

Project General Description

The works conceived as a separate system will involve: - construction of 60 km of major nad minor sewers; - construction of sewerage pumping station; - construction of a sewage treatment plant. The project constitutes stage 1 of the first phase of a planned sewerage system which will serve the entire city in the future. The area to be sewered under this project was selected by the consultants on the basis of technical, economic, and financial evaluations of sewering the various parts of the city. The selected area is in the central and southern part of the city encompassing the entire business area and the fastest developing residential and industrial areas.

Participating Organization

Funding
African Development Fund
Extending
Government Of Ethiopia
Implementing
Addis Ababa Water and Sewerage Authority

Information

IATI identifier 46002-P-ET-EB0-002
Last Update 31 Oct 2019

Export

Contact Details

Geographic Location

Country Ethiopia