Expansion of Glass Manufacturing Unit


Project Summary

Approval Date 17 Jan 1975
Signature Date 03 Jul 1975
Planned Completion Date 30 Jun 1979
Last Disbursement Planned Date 30 Jun 1979
Sovereign / Non-Sovereign Sovereign
Sector Industry, Minning & Quarrying
DAC Sector Code 32110
Commitment U.A 4,989,707.63
Status Completion

Project General Description

The main project activities include : i) geotechnical and site surveys; ii) preparation of detailed engineering design and tender documents; iii) manufacture and devivery of equipment; iv) erection and commissioning of the various components of the project; and v) supervision of project implementation.

Participating Organization

Funding
African Development Bank
Implementing
GHANA INDUSTRIAL HOLDING CORPORATION

Information

IATI identifier 46002-P-GH-B00-003
Last Update 29 Jul 2021

Export

Contact Details

Geographic Location

Country Ghana