Electricity Project II


Project Summary

Approval Date 24 Jan 1973
Signature Date 03 Jul 1973
Planned Completion Date 31 Dec 1976
Last Disbursement Planned Date 31 Dec 1976
Sovereign / Non-Sovereign Sovereign
Sector Power
DAC Sector Code 23630
Commitment U.A 3,000,000
Status Completion

Project General Description

This intervention relates to the Electricity project II. It concerns the extension and improvement of the Tangier-Tetouan region network and consists of the construction of five (05) transformer stations and 60 KV. As part of this project, the construction of the five (5) proposed transformer stations and new transmission lines is expected to replace the existing old network, which is in a state of constant danger to the inhabitants and to provide the region with the energy needed for its economic activities, particularly the development of its chemical industries. The project includes: (i) the construction of approximately 600 km of 225 KV lines; (ii) the raising the voltage of 340 km line from 150 to 225 KV; (iii) the construction or conversion to 225 KV of 9 major transformer stations.

Project Objectives

The project aims to extend and improve the network of the Tangier-Tetouan region. It should allow the construction of five (05) transformer stations and 60 KV.

Beneficiaries

The main beneficiaries of the project are the populations of the Tangier-Tetouan region.

Participating Organization

Funding
African Development Bank
Implementing
Office National de l'Electricité

Information

IATI identifier 46002-P-MA-FAC-002
Last Update 19 Oct 2020

Export

Contact Details

Geographic Location

Country Morocco