Line of Credit to Ndb I


Project Summary

Approval Date 22 Nov 1974
Signature Date 06 Jan 1975
Planned Completion Date 31 Dec 1977
Last Disbursement Planned Date 31 Dec 1977
Sovereign / Non-Sovereign Sovereign
Sector Finance
DAC Sector Code 24030
Commitment U.A 1,000,000
Status Completion

Project Objectives

1. overall objective : carry out a feasibility study for the development of hydroelectric projects for providing cheap and reliable power to the economy. 2. Specific objectives : determine the techno-economic feasibility of developing hydropower stations at Roseires, Sennar and Jebel Aulia Dams.

Participating Organization

Funding
African Development Bank
Implementing
National Development Bank LTD

Information

IATI identifier 46002-P-SL-HA0-001
Last Update 31 Oct 2019

Export

Contact Details

Geographic Location

Country Sierra Leone