Approval Date | 26 Oct 2010 |
Signature Date | 13 Dec 2010 |
Planned Completion Date | 31 Dec 2021 |
Last Disbursement Planned Date | 30 Sep 2020 |
Sovereign / Non-Sovereign | Sovereign |
Sector | Power |
DAC Sector Code | 23630 |
Environmental Category | 1 |
Commitment | U.A 83,178,749.98 |
Status | Completion |
The Iringa-Shinyanga Transmission Line Project involves the construction of an overhead line to reinforce the entire backbone transmission grid system of Tanzania. In order to avoid installing excess transmission capacity and reduce initial investment cost, the development of the project is divided into two (2) phases. Phase I of the project involves the construction of a 667 km long, 400 kV double-circuit backbone transmission interconnection, including the Fiber Optic Communication Line (FOCL) and the Shield Wire System (SWS). Phase II will comprise a system upgrade to 400 kV level for all associated substations (Iringa, Dodoma, Singida and Shinyanga) with the addition of 720 MVA shunt-reactor capacity. The planned upgrades will allow an increase in the transfer capacity to 1,000 MW. The implementation of the upgrade is scheduled for 2020 when the load on the line is expected to warrant that level. The existing 220kV line has already reached its technical limits and cannot handle this expected demand growth. In this context, the proposed project is of critical importance and forms part of TANESCO’s shortterm strategy for national grid transmission line reinforcement. Most of the line stretches will run parallel to the existing 220 kV line, with only minor variations in areas where alternative alignments have been proposed due to the topography of the terrain. The planned line is a 400 kV line and will have a length of approximately 670 km. It will interconnect four substations (S/S) at the Iringa, Dodoma, Singida and Shinyanga towns. The project is expected to be completed by the end of 2013 at an estimated cost UA 314 Million.
The project is designed to enable the transmission of adequate power to meet growing demand in Tanzania as well as meet the requirements of planned interconnection with neighbouring countries. The proposed new transmission line will considerably increase the power transfer capacity from the existing and future generating sources in the south to the load centres in the north and northwest of Tanzania.
The main project beneficiaries will therefore include (i) TANESCO as the project facilities will enable TANESCO to evacuate power from planned projects; (ii) households, industrial, mining and commercial electricity consumers to be connected to the national grid will also benefit from the new supply and increased reliability of service as a result of the project; the project will also benefit the rural population by facilitating the work of the Rural Energy Agency (REA).
Funding
African Development Fund
|
Funding
Accelerated Cofinancing Facility for Africa
|
Extending
Government Of Tanzania, United Republic of
|
Implementing
Tanzania Electric Supply Company LTD (TANESCO)
|
IATI identifier | 46002-P-TZ-FA0-009 |
Last Update | 24 Mar 2023 |
Name | Andrew MUGUWA |
a.muguwa@afdb.org |
Country | Tanzania, United Republic of |
Coordinates | Location Name |
---|---|
-6.58958 35.7001 | Dodoma Rural District |
-6.15973 35.798 | Dodoma Urban District |
-4.33333 33.75 | Igunga District |
-4.33333 34.5 | Iramba District |
-7.56399 34.8816 | Iringa Rural District |
-7.77 35.69 | Iringa Urban District |
-3.61666 33.8667 | Kishapu District |
-5 35.75 | Kondoa District |
-6.33333 34.5833 | Manyoni District |
-3.66667 33.5 | Shinyanga Urban |