Uganda - Community Agricultural Infrastructure Improvement Programme - Project 1 (CAIIP-P1)


Project Summary

Approval Date 31 Jan 2007
Signature Date 17 May 2007
Planned Completion Date 30 Jun 2014
Last Disbursement Planned Date 31 Dec 2014
Sovereign / Non-Sovereign Sovereign
Sector Agriculture and Rural Development
DAC Sector Code 43042
Environmental Category 2
Commitment U.A 28,424,955.84
Status Completion

Project General Description

The Community Agricultural Infrastructure Improvement Project-Phase 1 (CAIIP-1), which is an offshoot of the 7th pillar of the Agriculture Modernization Plan (MAP) - Physical Infrastructure, places special emphasis on improving the state of the roads and rural markets. It is a program with a total estimated cost of UA 34.20 million, the overall sectoral goal of which is to contribute to poverty reduction and economic growth in Uganda through better commercialization of agriculture. The program will have to be implemented over a period of five years. It comprises the following three components: (a) Improvement of rural infrastructure; (b) Community mobilization; and (c) Program coordination.

Project Objectives

The objectives of the project are to: improve farmers' access to markets, ensure competitive prices and increase income through the improvement of rural infrastructure and its management by highly mobilized communities.

Beneficiaries

The main beneficiaries of the project are the local communities as a whole (including small farmers, traders, transporters, consumers, contractors and suppliers). In total, approximately 1.76 million households will be affected by the project.

Participating Organization

Funding
African Development Fund
Extending
Government Of Uganda
Implementing
Ministère de l’Administration locale

Information

IATI identifier 46002-P-UG-AB0-001
Last Update 22 Nov 2020

Export

Contact Details

Name NUWAGIRA Asaph
Email a.nuwagira@afdb.org

Geographic Location

Country Uganda