Approval Date | 19 Jun 2019 |
Signature Date | 05 Sep 2019 |
Planned Completion Date | 30 Apr 2020 |
Last Disbursement Planned Date | 30 Apr 2020 |
Sovereign / Non-Sovereign | Sovereign |
Sector | Power |
DAC Sector Code | |
Commitment | U.A 1,290,975.64 |
Status | Implementation |
The proposed operation concerns the consolidation work of the Emergency Power Infrastructure Rehabilitation Project (EPIRP) in Zimbabwe. The Project is critical to the rehabilitation of the country power system network and will improve the availability and reliability of electricity supply thereby supporting water supply and sanitation delivery as well as agriculture irrigation needs. The implementation of the Emergency Power Infrastructure Rehabilitation Project (EPIRP) has been done in two phases with Phase I having been completed in April 2016. The Consolidation Works implementation will be completed within the new Zimbabwe Multi-Donor Trust Fund (ZimFund) mandate which expires on of 20 October 2020. These Consolidation Works is comprised of two main components: (i) supply and installation of substation ancillaries and equipment; and (ii) Project Management.
The main objective is to improve the availability and reliability of electricity supply at Stamford (Harare), Mpopoma & Hillside (Bulawayo), and Matabeleland North, which were partly covered under Phase I project.
The main beneficiaries are the populations of the targeted areas, including Stamford (Harare), Mpopoma and Hillside (Bulawayo), and Matabeleland North.
Funding
Zimbabwe Multi-donor Trust Fund
|
Implementing
ZIMBABWE ELECTRICITY SUPPLY AUTHORITY
|
IATI identifier | 46002-P-ZW-FA0-018 |
Last Update | 31 Oct 2019 |