IATI identifier Country Sector Sovereign / Non-Sovereign Title Commitment in UA Status Signature Date
46002-P-CI-FA0-017 Cote d'Ivoire Power Sovereign Cote d'Ivoire - Project to Improve Access to Electricity in Rural Areas 34,550,621 Implementation 28 Feb 2019
46002-P-BF-FA0-010 Burkina Faso Power Sovereign Burkina Faso – Initiative « Désert à l’énergie » - Projet Yeleen électrification rurale 3,000,000 Implementation 28 Feb 2019
46002-P-Z1-F00-077 Multinational Power Sovereign Multinational - Burundi-Rwanda Power Grid Interconnection Project for Nelsap 3,170,000 Implementation 21 Feb 2019
46002-P-ZA-FA0-003 South Africa Power Sovereign South Africa - Eskom Transmission Improvement Project - Loan 7,948,967 Implementation 27 Nov 2018
46002-P-TZ-FA0-013 Tanzania, United Republic of Power Sovereign Tanzania - North West Grid (400 KV Nyakanizi-Kigoma Transmission Line 64,562,633 Implementation 15 Nov 2018
46002-P-CM-F00-006 Cameroon Power Non Sovereign Private Sector Credit Enhancement Facility (PSF) - Recommended Multi - Sector Risk Participations 106,158,846 Completion 08 Nov 2018
46002-P-RW-FA0-016 Rwanda Power Sovereign Rwanda - Scaling Up Electricity Access Program Phase II (SEAP II) 189,373,369 Implementation 16 Oct 2018
46002-P-GW-FA0-005 Guinea-Bissau Power Sovereign Guinea-Bissau - Bissau City Power Distribution System Improvement Project 20,000,000 Implementation 31 Aug 2018
46002-P-Z1-FA0-119 Multinational Power Sovereign Multinational - Nigeria-Niger-Benin-Burkina Faso Power Interconnection Project 36,500,000 Implementation 25 Jun 2018
46002-P-UG-FAB-008 Uganda Power Non Sovereign Uganda - Bujagali Energy Limited 2 46,697,704 Implementation 22 Jun 2018
46002-P-DJ-FA0-003 Djibouti Power Sovereign Djibouti – Geothermal Exploration Project in the Lake Assal Region 10,740,000 Implementation 08 May 2018
46002-P-Z1-FA0-146 Multinational Power Sovereign BURKINA FASO-PROJET D'INTERCONNEXION NIGERIA-NIGER-BENIN-BURKINA FASO 34,680,000 Implementation 14 Mar 2018
46002-P-Z1-FA0-152 Multinational Power Sovereign Multinational - Projet d’interconnexion électrique Cameroun- Tchad (composante Tchad) 27,500,000 Implementation 07 Mar 2018
46002-P-BJ-FA0-004 Benin Power Sovereign Benin - Electricity Corporation of Benin Sub-Transmission and Distribution System Restructuring and Extension Project (PRESREDI) 11,610,000 Implementation 06 Mar 2018
46002-P-MG-FA0-016 Madagascar Power Sovereign Madagascar - Etude de faisabilité du projet de renforcement et d'interconnexion des réseaux de transport d'énergie électrique 1,000,000 Implementation 12 Feb 2018