46002-P-NE-F00-004 Niger Power Sovereign Niger - Rural, Semi-Urban and Urban Electrification Project 51,720,000 Implementation 09 Dec 2016
46002-P-CD-FA0-011 Congo, the Democratic Republic of the Power Sovereign Democratic Republic of Congo - Power Sector Improvement and Governance Support Project 96,100,000 Implementation 07 Dec 2016
46002-P-Z1-F00-066 Multinational Power Sovereign Multinational - Mozambique - Zambia 400KV Power Interconnector Project 1,390,515 Implementation 06 Dec 2016
46002-P-MG-F00-002 Madagascar Power Sovereign Madagascar - Energy Sector Reform Support Programme 13,770,000 Completion 25 Nov 2016
46002-P-Z1-F00-065 Multinational Power Sovereign Multinational - The Kolwezi (DRC)-Solwezi (Zambia) 330 kV Power Interconnector Project 1,456,535 Implementation 24 Nov 2016
46002-P-CI-FA0-014 Cote d'Ivoire Power Sovereign Côte d’Ivoire - Power Transmission and Distribution Networks Reinforcement Project 109,473,918 Implementation 16 Nov 2016
46002-P-Z1-FA0-115 Multinational Power Sovereign Multinational - The Interconnection of Electric Grids of Nile Equatorial Lakes Countries (Supplementary Loan to the Republic of Uganda) 985,725 Completion 15 Nov 2016
46002-P-BF-FA0-007 Burkina Faso Power Sovereign Burkina Faso - Electrification of Semi-Urban Areas of Ouagadougou and Bobo-Dioulasso Project 27,230,000 Implementation 21 Sep 2016
46002-P-ET-FA0-011 Ethiopia Power Sovereign Ethiopia - Mekele-Dallol and Semera-Afdera Power Supply for Industrial Development and Access Scale-up Project 76,953,633 Implementation 14 Jul 2016
46002-P-Z1-FA0-104 Multinational Power Sovereign Multinational - Interconnection of the Electric Grids of the Nile Equatorial Lakes Countries 8,040,000 Implementation 05 Jul 2016
46002-P-KE-FA0-013 Kenya Power Sovereign Kenya - Last Mile Connectivity Project II 99,044,424 Implementation 27 Jun 2016
46002-P-Z1-FA0-076 Multinational Power Sovereign Multinational- Ruzizi III regional hydropower plant project (Burundi) 19,290,000 Implementation 16 Dec 2015
46002-P-Z1-FA0-077 Multinational Power Sovereign Multinational- Ruzizi III regional hydropower plant project (Rwanda) 16,000,000 Implementation 16 Dec 2015
46002-P-Z1-FA0-078 Multinational Power Sovereign Multinational - Ruzizi III regional hydropower plant project 60,000,000 Implementation 16 Dec 2015
46002-P-Z1-FA0-105 Multinational Power Sovereign Multinational- Ruzizi III regional hydropower plant project 1,710,000 Implementation 16 Dec 2015